1957 – process initiated



1961
This was the first ever quinquennial inspection and was carried out by Mr. Cecil Upsher.
All rights reserved by Norfolk Record Office who hold the original; their ref is NRO PD 485/22
1983
Image courtesy of Lambeth Palace Library
1989
Image courtesy of Lambeth Palace Library
2002
2012
2017
2017 summary
The following is a summary of the above 2017 quinquennial (at 2017 prices):-
| South Aisle and south porch roofs | 67,000.00 | |
| South Aisle Buttresses | 6,000.00 | |
| South Aisle Walls | 2,000.00 | |
| South Porch Walls | 2,500.00 | |
| Conserve porch arch | 6,000.00 | |
| Priority B – Structure | ||
| All repairs in QIR | 61,000.00 | |
| Priority C – Structure | ||
| All repairs in QIR | 27,000.00 | |
| Priority D – Structure | ||
| All repairs in QIR | 75,500.00 | |
| Sub total | 247,000.00 | |
| Preliminary Costs, say, | 5,000.00 | |
| Scaffolding/Access | 30,000.00 | |
| Sub total | 282,000.00 | |
| Contingency @ 10% | 28,200.00 | |
| Sub total | 310,200.00 | |
| Plus architect’s fees @ 11% | 34,122.00 | |
| Sub total | 344,322.00 | |
| Plus VAT @ 20% | 68,864.40 | |
| Total | 413,186.40 | |
| Not included:- | ||
| Three-phase electrics | ||
| Making good interior plasterwork | ||
| Redecoration of interior | ||
| Improving heating | ||
| Bat surveys and mitigation | ||
| Repairs to floors and pews | ||
| Etc |
2022
| Date | Change |
|---|---|
| 4/6/24 | 1989 |
| 29/11/23 | Full 1961 report |
| 18/10/23 | Smaller file size for 2002 |
| 10/10/23 | 2002 & 2022 |
| 7/9/23 | 1957/61 documents |
| 31/8/23 | Published |